The Time axis tab allows you to configure the information displayed along the temporal axis of the Time-Location schedule.

These elements form the time scales used to identify dates and periods in the view.

Several scale lines can be displayed simultaneously to improve the readability of the schedule.

For example:

  • months
  • weeks
  • days


The interface is composed of two main sections:

  • management of the time lines
  • editing the parameters of a line

The upper section allows you to add, remove or reorganise the different scale lines.

The lower section allows you to modify the parameters of the selected line.


As with the distance axis, time scales can be displayed on two sides of the schedule:

  • Time line
  • Opposite time line

This allows time markers to appear on multiple edges of the view.


Two types of lines can be used to display time markers:

  • single line
  • composite line

The following sections explain how to configure each of these line types.