Display tab

The Display tab allows you to control the graphical elements displayed in the Time-Location view.

These settings only affect the visualisation of the schedule and have no impact on the project data.

Two categories of settings are available in this tab.


The first section allows you to enable or disable the display of certain graphical elements of the schedule.

It is possible to show or hide:

  • annotations

text attached to activities

  • links

relationships between activities

  • critical path

highlights the critical activities in the schedule

  • free float
  • total float

These options make it possible to adapt the readability of the schedule depending on the level of analysis required.

For example:

  • display the critical path to analyse schedule risks
  • hide links to simplify the diagram display

The second section concerns the display of the calendar in the background of the schedule.

You can choose:

  • the calendar to display
  • the level of calendar detail

Depending on the selected options, it is possible to display:

  • working periods
  • non-working periods

This information appears directly in the background of the schedule and makes it easy to quickly identify working periods and downtime periods.