Add a single line
A single line allows regular time markers to be displayed along the time axis.
It is generally used to display:
- months
- weeks
- days
Displayed value
The Displayed value field allows you to define the information that will appear in the scale.
For example:
- Month (Jan, Feb, Mar…)
- Week
- Day
- Year
Display interval
The Interval every parameter defines how frequently the markers are displayed.
For example:
- 1 month
- 1 week
- 1 day
This allows the level of detail of the scale to be adjusted.
Formatting
The following parameters allow the appearance of the time line to be adjusted:
- font
- text size
- column width
- text position
- background colour
These settings improve the readability of the Time-Location schedule.