Copying or updating a deliverable

It is possible to update an existing deliverable or create a copy in order to adapt its content to the evolution of the project.

To access this function:

  1. right-click on the deliverable name
  2. select Copy and/or update

An interface then opens to configure the modifications to apply.


You can choose whether to:

  • keep the existing customizations
  • or update the settings from the phasing design.

The affected parameters include:

  • status colors
  • clipping
  • the order of zones and axes

The order of zones and axes can also be updated according to:

  • zone priorities
  • the order of statuses defined in the project settings

Sheets can be modified individually.

For each sheet, it is possible to:

  • modify the start date and time
  • modify the end date and time
  • change the associated plan
  • delete certain sheets

It is also possible to apply a global time shift to the dates of all sheets.

This makes it easy to adjust the schedule of the entire deliverable.


Once the parameters are defined, two options are available:

  • update the existing deliverable
  • create a new deliverable based on it

This feature allows you to quickly duplicate a deliverable while preserving its configuration.