In deliverables, the zones affected by the works can display different states in order to represent the progress of activities.
By default, zones inherit the conditional formatting defined in the label template being used.
Using zone states makes it easier to visualize the progress of the works.
Main status
Four main status are used to represent the progress of the works:
- In progress : one or more activities are currently being executed in this zone
- Started : at least one activity has already taken place in this zone, but other activities are still planned later
- Completed : all activities planned in this zone are finished
- To do : no activity has yet started in this zone
Specific status
Two additional status may appear in certain situations:
- Impact : the zone is impacted by works carried out in another zone
- Right-of-way : works on an axis require a wider work area than the intervention zone
Defining status colors
The colors associated with the states can be defined:
- by default in Project → Properties → Project → Default options
- for a specific deliverable in the Zone and axis states tab
The arrow located to the left of a color allows you
to apply this configuration to the following sheets.
Displaying completed zones
For each sheet, it is possible to choose whether completed zones should remain visible.
This option is available in the lower panel of the deliverable:
- open the Zones tab
- expand the Completed section
Available options:
- Visible : display the completed zone
- Apply : apply this setting
to the following sheets