Activities represent the operations carried out within the project. They can be associated with zones or axes in order to represent their location and progression within the phasing.


To create an activity from a zone:

  1. click on the zone label
  2. the zone editing window appears
  3. click Properties, then Add
  4. an activity editing window opens where the activity can be configured

The activity is then linked to the selected zone.

It is also possible to add an existing activity to the zone using the following drop-down menu:


Summary activities allow you to group several activities within the same phase.

To create an activity:

  1. select the sub-project in the left panel of the Gantt
  2. select an existing activity
  3. click the Add button

A new activity appears in the Gantt.

Its information can then be modified:

  • directly in the columns
  • via the Edit menu accessible with a right-click

For example:

  • Name: Phase 1: North roundabout (1/2)
  • ID: 1

An activity becomes a summary activity when it has at least one child activity.

To do this, simply drag an activity beneath it in the Gantt.


  1. From the Gantt located below the plan workspace, an activity can be dragged directly onto a zone or axis to associate it.
  2. This association can also be done from the activity editing window by opening the ZONE tab.