Table organisation
The table located on the left side of the Gantt chart allows you to display and organise the information associated with the schedule activities.
This table can be customised to adapt the display to the needs of the project analysis.
The main available actions are:
- adding or removing columns
- sorting activities
- organising the hierarchy
- customising structure colours
Adding a column
The table can display many pieces of information about the activities.
To add a column:
- right-click on a column header
- select Add column
A list of available fields will then appear, for example:
- ID
- Name
- Zone
- Start
- Finish
- Duration
- Quantity
- Productivity
- Progress
- Description
The selected column is immediately added to the table.
This allows the schedule view to be adapted according to the information needed for analysis.
Removing a column
To remove a column from the display:
- right-click on the column header
- select Remove column
This action does not delete the project data, but only removes the column from the display.
Sorting activities
Activities can be sorted directly from the column headers.
To sort the data:
- click on the desired column header
Sorting can be applied on multiple levels.
Each click adds an additional sorting level, allowing for example:
- sorting by Name
- then by Start date
- then by Finish date
This sorting makes it easier to analyse the schedule and find activities.
Modifying the hierarchy organisation
Project activities are organised within a hierarchical structure:
- Project
- Subproject
- Activities
- Sub-activities
It is possible to choose what should be displayed by expanding or collapsing hierarchy levels.
To access these options:
- open the hierarchy menu
- select Re-organize the tree
Changing hierarchy colours
The different hierarchy levels can be displayed with distinct colours to make the schedule easier to read.
To modify these colours:
- open the hierarchy menu
- select Modify tree colours
You can then define a colour for:
- Project
- Subproject
- Parent
- Activity
These colours improve table readability and allow quick identification of structure levels.
Customising the table display
The table organisation is fully configurable.
Each user can therefore:
- display only the necessary columns
- sort activities according to their needs
- adapt structure colours
- organise the project hierarchy
This customisation allows the Gantt table to become a true schedule analysis tool.



