Each activity in Tilos360 is associated with a calendar. By default, four calendars are available:
Calendars can be accessed using the navigation button
Calendars are based on the following elements:
periods (generally weeks).day definition, which defines the number of working hours.working time ranges.These elements are configured in this interface.
For each type of day (Working day, bad weather, holidays, etc.), a day definition must be created and assigned one or more working time ranges.
You must then define a period composed of the previously defined days. A period consists of a minimum of 1 day and a maximum of 7 days.
Choose the number of days for the period and assign each day to the desired day definitions.
You can then define the default project calendar by creating or editing a calendar.
Add the previously created periods.
A period remains active until another period interrupts it.