Activities represent the operations carried out within the project. They can be associated with zones or axes in order to represent their location and progression within the phasing.
To create an activity from a zone:
The activity is then linked to the selected zone.
It is also possible to add an existing activity to the zone using the following drop-down menu:
Summary activities allow you to group several activities within the same phase.
To create an activity:
A new activity appears in the Gantt.
Its information can then be modified:
For example:
An activity becomes a summary activity when it has at least one child activity.
To do this, simply drag an activity beneath it in the Gantt.