The Gantt chart provides several tools that allow you to adjust the schedule display and easily navigate through the project activities.
These tools make it possible to:
A right-click on the time scale provides access to the time display options.
Available actions include:
Some options also provide direct access to filtering, grouping, or rescheduling tools.
The toolbar located above the Gantt chart allows quick actions on the schedule display and organisation.
It provides several features.
The Zone filter displays only the activities associated with a specific project zone.
This filter is particularly useful for linear projects or projects containing several work areas.
The Start and Finish fields allow activities to be filtered according to a selected time range.
Two modes are available:
within the selected period
The Advanced filter button allows the definition of more precise criteria to display certain activities.
Activities can be filtered according to various project fields.
The Grouping function organises activities according to a specific criterion.
For example:
Grouping improves schedule readability and analysis.
The Activity display menu allows modification of how activities appear in the Gantt chart.
Activities can be coloured according to:
This improves the readability of the schedule.
The + button allows a new activity to be quickly added to the schedule.
The Reschedule button recalculates the schedule dates according to the links and constraints defined between activities.
Navigation in the Gantt chart can be performed in several ways:
These tools make it possible to navigate efficiently even in schedules containing a large number of activities.