====== Creating links between activities ====== In a Time-Location schedule, **links between activities** define the logical relationships between different operations. These links allow you to represent: * the sequence of works * dependencies between activities * succession constraints between crews They therefore help structure the schedule and ensure the logical consistency of the workflow. {{:en:time_distance:2026-03-12_22h38_03.png?400|}} ----- ===== Selecting activities ===== To create a link between two activities, first select the activities involved. Hold the **CTRL** key on the keyboard and click successively on the activities to be linked. The selection order is important: * the **first selected activity** is the **predecessor** * the **second selected activity** is the **successor** This defines the direction of the link in the schedule. ----- ===== Creating the link ===== Once the activities are selected: - **right-click** in the Time-Location view - select the **Create link** menu Several options are available: * **Link two activities** creates a direct link between the two selected activities * **Link a sequence** automatically creates successive links between several activities * **Link multiple activities** allows several links to be created simultaneously ----- ===== Link visualisation ===== Once created, the link appears directly in the Time-Location view as a **segment connecting the two activities**. This link represents the logical relationship between operations and allows dependencies in the schedule to be quickly visualised. Links help with: * analysing the logical sequence of works * identifying dependencies between crews * understanding the overall workflow of the project ----- ===== Rescheduling the project ===== After creating or modifying links between activities, it is necessary to **recalculate the schedule** so that dependencies are taken into account. To do this, click the **Reschedule** button located at the bottom right of the interface. {{:fr:espace_temps:2026-03-06_17h31_51.png?200|}} Rescheduling allows you to: * recalculate activity dates * apply the constraints defined by the links * update the logic of the schedule This operation ensures that the schedule correctly reflects the relationships between activities. ----- ===== Modifying or deleting a link ===== As with activities, links can be modified or deleted from the **context menu** accessible by right-clicking. This allows the schedule logic to be easily adjusted when the organisation of the works evolves. In a Time-Location schedule, it is recommended to create links in the **direction of project progression** to maintain a clear and logical reading of the schedule.