====== Status management ====== In deliverables, the zones affected by the works can display different **states** in order to represent the progress of activities. By default, zones inherit the **conditional formatting** defined in the label template being used. Using **zone states** makes it easier to visualize the progress of the works. ----- ===== Main status ===== Four main status are used to represent the progress of the works: * **In progress** : one or more activities are currently being executed in this zone * **Started** : at least one activity has already taken place in this zone, but other activities are still planned later * **Completed** : all activities planned in this zone are finished * **To do** : no activity has yet started in this zone ----- ===== Specific status ===== Two additional status may appear in certain situations: * **Impact** : the zone is impacted by works carried out in another zone * **Right-of-way** : works on an axis require a wider work area than the intervention zone ----- ===== Defining status colors ===== The colors associated with the states can be defined: * by default in **Project → Properties → Project → Default options** {{:en:phasing:2026-03-13_11h40_48.png?600|}} * for a specific deliverable in the **Zone and axis states** tab {{:en:phasing:2026-03-13_11h41_30.png?400|}} The arrow located to the left of a color allows you to **apply this configuration to the following sheets**. ----- ===== Displaying completed zones ===== {{:en:phasing:2026-03-13_11h47_02.png?600|}} For each sheet, it is possible to choose whether **completed zones** should remain visible. This option is available in the **lower panel** of the deliverable: - open the **Zones** tab - expand the **Completed** section Available options: * **Visible** : display the completed zone * **Apply** : apply this setting to the following sheets