====== Display and navigation ====== The **Gantt chart** provides several tools that allow you to adjust the schedule display and easily navigate through the project activities. These tools make it possible to: * modify the time scale * show or hide certain Gantt elements * filter activities * adjust the schedule visualisation ----- ===== Time scale management ===== {{:en:gantt:2026-03-12_11h51_14.png?400|}} A **right-click on the time scale** provides access to the time display options. Available actions include: * **Add time line** *Adds an additional scale level (years, months, weeks, days, hours or minutes). * **Delete time line** *Removes the selected time scale line. * **Properties** *Allows modification of the time scale parameters. * **Show / Hide grid** *Displays or hides the grid corresponding to the selected time scale. * **Adjust time scale** *Automatically adjusts the Gantt scale so that all visible activities are displayed. * **Show / Hide time indicator** *Displays a marker indicating the current date or time. * **Change background colour** *Changes the background colour of the header containing the time scale. * **Layout** *Adjusts the position of the texts in the time scale. * **Font** *Changes the font used in the display. Some options also provide direct access to **filtering**, **grouping**, or **rescheduling** tools. ----- ===== Gantt toolbar ===== {{:en:gantt:2026-03-12_11h51_54.png?600|}} The toolbar located above the Gantt chart allows quick actions on the schedule display and organisation. It provides several features. ----- ==== Filter by zone ==== The **Zone** filter displays only the activities associated with a specific project zone. This filter is particularly useful for **linear projects** or projects containing several work areas. ----- ==== Filter by time period ==== The **Start** and **Finish** fields allow activities to be filtered according to a selected time range. Two modes are available: * **Between**: displays activities intersecting the period * **Strict**: displays only activities fully contained within the selected period ----- ==== Advanced filter ==== The **Advanced filter** button allows the definition of more precise criteria to display certain activities. Activities can be filtered according to various project fields. ----- ==== Grouping ==== The **Grouping** function organises activities according to a specific criterion. For example: * by zone * by activity type * by category Grouping improves schedule readability and analysis. ----- ==== Activity display style ==== The **Activity display** menu allows modification of how activities appear in the **Gantt chart**. Activities can be coloured according to: * their **style** * their **colour** * the **associated zone** * certain **activity fields** This improves the readability of the schedule. ----- ==== Add an activity ==== The **+** button allows a new activity to be quickly added to the schedule. ----- ==== Reschedule ==== The **Reschedule** button recalculates the schedule dates according to the links and constraints defined between activities. ----- ===== Navigating the schedule ===== Navigation in the **Gantt chart** can be performed in several ways: * by moving the view horizontally along the timeline * by using filtering tools * by adjusting the time scale * by collapsing or expanding hierarchy levels These tools make it possible to navigate efficiently even in schedules containing a large number of activities.